PJM Interconnection proposes data center power management plan; stakeholder feedback is mixed on implementation approach.
PJM Interconnection, the 13-state regional power grid operator, submitted its proposal for an Interim Resource Adequacy Service (IRAS) and a Large Load Registry to the Federal Energy Regulatory Commission in August. The plan would track Large Loads with significant power demands—50 megawatts or more—and establish a mechanism for those that don't provide their own power to reduce demand when the grid reaches dangerous strain levels.
Dozens of responses to FERC have produced thousands of pages of feedback. Democratic Rep. Frank Pallone Jr., ranking member of the House Energy & Commerce Committee, supports some of PJM's proposals but believes they don't go far enough to protect mid-Atlantic families. He notes that data centers have driven a $30 billion increase in PJM capacity market costs since summer 2024—costs ultimately borne by consumers. "The only way out is more generation, and the data centers responsible for PJM's issues should be the ones responsible for finding and incentivizing generation to fix those issues." While acknowledging FERC cannot allocate costs directly to data centers, Pallone urges the commission to allocate them instead to zones fueling data center growth. He supports a public Large Load Registry, calling it "invaluable for improving forecasts of electricity demand, which even PJM has noted needs drastic improvement."
The Data Center Coalition opposes the plan primarily on states' rights grounds. It argues that while PJM claims states will have "complete discretion" over IRAS implementation, states actually have no ability to opt in or out. PJM will unilaterally decide on curtailing new Large Load customers regardless of individual state preferences, forcing states to comply or risk subjecting all retail customers to interruption. The coalition also contends that IRAS will make customers in zones with new Large Loads subsidize rate reductions for others across the PJM footprint. It calls for FERC to reject the proposal entirely and work with stakeholders and states on alternative emergency procedures. If FERC does not reject IRAS outright, the coalition urges a "meaningful transition mechanism" and implementation delay until June 1, 2028.
Google argues that IRAS will worsen the generation capacity shortage problem. The company is actively procuring new capacity to cover its projected load growth but says IRAS will discourage large customers from bringing their own new capacity. Instead, Google proposes an interruptible service model similar to natural gas transportation—where capacity receives lower priority and doesn't guarantee delivery, allowing "supply and demand to clear in the capacity market without creating pervasive uncertainty that would interfere with investment in new capacity."
PJM defends its plan as a region-wide response to operational emergencies caused by the influx of new Large Loads, one that respects the jurisdictions of the 13 PJM states and the District of Columbia at the retail level. The company asserts that IRAS is "just and reasonable and not unduly discriminatory or preferential," and describes it as a framework that "accommodates and in fact welcomes further state action" while "maintaining resource adequacy, reliability and affordability."