Saturday, October 10, 2026
AI Infrastructure · News & Analysis
Home › Power & Energy › Report
Power & Energy · Report

PJM Interconnection has granted fast-track interconnection approval to Engie and LS Power totaling 2.1 GW, including Engie's two storage projects of nearly 1.7 GW and LS Power's 455-MW gas-fired uprate.

Fast-tracked capacity in the PJM region, largely storage and gas, helps ease the grid bottleneck facing data center developers by adding near-term supply.
Trade pressSlicast · October 9, 2026 at 14:27 UTC · Global · Source: Utility Dive
importance 72

The PJM Interconnection has approved three initial projects totaling 2.1 GW in its Expedited Interconnection Track process, the grid operator said Thursday. The projects are two energy storage projects planned by Engie IR Holdings and a gas-fired uprate proposed by an LS Power unit. PJM expects all three to come online in mid-2029.

With the approvals in hand, Engie plans to build an 860-MW storage project in Crawford, Pennsylvania, and an 800-MW storage project in Morrow, Ohio, according to PJM.

LS Power intends to add 455 MW to its 810-MW combined-cycle Hunterstown power plant in Adams, Pennsylvania, PJM said. LS Power bought the power plant from Platinum Equity in 2024.

The projects' advancement through PJM's review comes as the grid operator faces tight supply conditions. Little generation has come online in recent years, while data centers are driving PJM's demand forecasts higher. That dynamic has led to a sharp spike in PJM's capacity costs, which is raising electric utility bills in some areas.

After the Federal Energy Regulatory Commission approved the Expedited Interconnection Track process in June, PJM opened the application window on July 31. The fast-track interconnection review is for projects larger than 250 MW that are backed by a primary siting authority and can begin operating within three years, PJM said.

Under the process, PJM will consider up to 10 interconnection requests a year for new or uprated capacity resources that meet the eligibility requirements. The process is set to expire at the end of 2027.

The temporary interconnection process is one part of PJM's broader effort to bring new generation online to meet rising demand, which is mainly driven by planned data centers, the grid operator noted. Those efforts include a pending reliability backstop procurement for new generation, updates to the grid operator's surplus interconnection service rules that could allow new generation to use existing interconnection capacity, and a reformed generator interconnection process.

Read the original
PJM Interconnection has granted fast-track… · Slicast