AWS is locking in land and power early for data-center sites but is holding off on installing servers until customers commit.

This sequencing shows hyperscalers securing grid and site capacity first while deferring server capex, so near-term AI chip shipments will track customer commitments rather than land banking.
Trade pressSlicast · November 25, 2026 at 13:21 UTC · US · Source: Crypto Briefing
importance 60

Amazon Web Services is splitting its data center buildout into two speeds. It secures land, power and permits early, and it waits to buy servers until customers commit.

**The slow part goes first**

Servers can be ordered on short notice. A grid connection, a zoning approval and a few hundred acres in the right location cannot.

AWS has been buying those scarce inputs. The company has put more than $170 million into land acquisitions in Northern Virginia, including a $99.79 million purchase of a former plant earmarked for a data center.

Indiana has drawn even more attention. On November 16, 2026, AWS broke ground on Project Rise, a $7 billion data center campus in Wheatfield. The plan calls for nine buildings across 304 acres. The campus is one part of a broader $33 billion investment spanning multiple Indiana sites.

Power is the other bottleneck AWS is working to get ahead of. The company added 3.9 GW of power capacity in 2025 and aims to double that figure by the end of 2027.

**Demand is not the problem**

In October 2026, the cloud unit reported a backlog of $578 billion and third-quarter sales of $46 billion.

Spending is rising to match. AWS is projected to spend roughly $220 billion on capital expenditures in 2026, and expectations point to significant increases again in 2027.

Much of that money is going to AI hardware. AWS set up what it calls the Early Rack Receipt Process to acquire Nvidia GB300 server racks well before they enter service. The program started at approximately $5 billion in August 2026 and has continued at around $3 billion per month since then. It lets AWS record the racks as assets before they are deployed.

**When the racks arrive before the power does**

That gap has already appeared. Power shortages at several US sites have left finished racks sitting in warehouses instead of running workloads.

The obstacles are not limited to the grid. AWS has also faced local opposition, permitting delays and grid connection problems in various states.