Three data-center projects are planned around Phoenix, Arizona, in Buckeye, Eloy and Casa Grande.

The three sites extend the Phoenix-area development pipeline for AI-scale campuses, where power and water availability will likely determine which projects proceed.
Trade pressSlicast · November 25, 2026 at 13:27 UTC · Global · Source: Data Center Dynamics
importance 55

**Fortescue looks to build data centers in Buckeye**

First reported by Azbex, Phoenix Hydrogen Hub LLC is requesting a Conditional Use Permit (CUP) from the City of Buckeye for a data center campus on approximately 157 acres located west of the northwest corner of State Route 85 and Patterson Road.

The property sits close to the planned Woolsey Peak substation, east of Phoenix, and is currently zoned Heavy Industrial (I-2). The proposed development includes three 100MW data center buildings, an approximately 300MW natural gas-fired generating plant, and battery energy storage systems (BESS). Known as the Buckeye Energy Campus, the project would total 1.725 million square feet (162,766 square meters).

The project would initially draw 120MW of electricity from Arizona Public Service (APS), with future on-site natural gas generation intended to serve the campus. Closed-loop cooling systems would be used to reduce water consumption.

The site, located at 28400 W Patterson Road, has historically been used for agriculture. It was originally rezoned for a hydrogen gas production facility that was canceled last year. Australian energy and metals company Fortescue is behind Phoenix Hydrogen LLC.

**Southwest Crossing Phase II comes to Eloy**

In Eloy, CRG, the real estate development arm of Clayco, has requested an Amendment to the Zoning Map (Rezone) for approximately 152 acres on the northwest corner of Tweedy and Battaglia Roads. The request would change the land from Light Industrial (I-1) to I-2 General Industrial with a Planned Area Development Overlay (PAD) to allow for data center development.

The 400MW, 1.2-million-square-foot (111,483 square meter) project is known as Southwest Crossing Phase II. Up to seven two-story data center buildings, each approximately 160,000 square feet (14,864 square meters), are planned, along with an on-site substation.

Phase I of the project was approved last year and is also set to include seven buildings and an on-site substation.

Eloy is a city in Pinal County, around 50 miles (80.4 km) southeast of Phoenix. The Loretta J. Haugen Trust is listed as the property owner.

**Casa Grande could bring PhoenixMart back to life**

AZ Sourcing LLC and Phoenix Mart LLC are seeking to amend a portion of a previously approved Planned Area Development into the Casa Grande Tech Center.

The campus would occupy more than 230 acres south of Florence Boulevard and west of Interstate 10 in Casa Grande. Plans call for on-site power generation using natural gas and battery energy storage, as well as rooftop solar.

The property is zoned Industrial (I-2), where data centers are an allowable use subject to approval of a Conditional Use Permit.

The site was previously earmarked for PhoenixMart, a 1.5-million-square-foot (139,354 square meter) commercial trade and wholesale hub first proposed in 2011 that was never completed. A large, empty shell building was constructed and would be reused as a data center.

According to a government announcement, no specific end user or data center operator has been identified at this time.

Casa Grande is located around 50 miles (80.4 km) southeast of Phoenix in Pinal County, close to Eloy.

Another large-scale project is also planned in the area. The Casa Grande Planning and Zoning Commission approved a Conditional Use Permit (CUP) for the proposed 954-acre Grande Valley Data Center campus at its October 1 meeting. The project is located south of Montgomery Road and Maricopa-Casa Grande Highway.