Vistra files 10-Q: quarterly report (10-Q)

Quarterly report — latest revenue, margins and guidance.
Official disclosureSlicast · August 10, 2026 at 12:00 UTC · US · Source: SEC EDGAR · VST

The following discussion and analysis of our financial condition and results of operations should be read together with the condensed consolidated financial statements and related notes included in Part I, Item 1. Financial Statements .

Business Environment and Outlook

Electricity Demand

Electricity demand drivers including the rise of large scale data centers, the electrification of oil field operations, and electric vehicle load building are contributing to a projected fast-paced load growth in the regions we serve. Our integrated retail electricity and power generation operations allow us to quickly respond to electricity demand changes. To support growing demand from large‑scale electricity consumers, we continue to engage in discussions with various counterparties regarding the potential long-term sale of power from our generation facilities, and we are progressing a series of development initiatives across our generation portfolio, including nuclear uprates and other capacity expansions.

Supply Chain Constraints

Our industry continues to face ongoing supply chain constraints and labor shortages, which have reduced the availability of essential equipment and supplies for constructing new generation facilities, increased the lead times for procuring materials, and raised equipment and labor costs associated with maintaining our natural gas, nuclear, and coal fleet.

We are proactively managing these constraints by continuously re-evaluating the business cases and timing of our planned development projects. This has led to the deferral or abandonment of some planned capital expenditures for our solar and battery projects and could impact the economic feasibility of additional projects in our new generation development pipeline. We are engaging with suppliers to secure key materials needed to maintain our existing generation facilities before future planned outages.

Iran Conflict

We are monitoring the conflict involving the United States, Israel, and Iran and related instability in the Middle East, including the potential for further escalation and disruption. Although the Company does not conduct operations in the affected region, prolonged or expanded instability could indirectly affect the Company through broader macroeconomic and commodity-market impacts, including changes in natural gas and power prices, supply-chain disruptions, construction delays, increased inflationary pressures, and capital-market volatility, which could impact our future results of operations. See Factors Affecting Our Financial Condition and Results of Operations — Commodity Prices for additional information on our commodity hedging strategy and estimated hedging levels for the balance of 2026 and 2027.

Noteworthy Developments Capacity Markets — PJM Auction Results

In July 2026, Vistra received its results from the PJM Capacity Auction for planning year 2028-2029, and the table below lists clearing price per MW-day and our cleared capacity volumes by zone:

VISTRA CORP.

Strategic Investment in Digital Infrastructure

Gas Plants Disposition

Planned Gas-Fueled Dispatchable Power in ERCOT

In May 2024, we announced our intention to add up to 2,000 MW of dispatchable, natural gas-fueled electricity capacity in west, central, and north Texas consisting of the following projects:

• Building up to 860 MW of advanced simple-cycle peaking plants to be located in west Texas to support the increasing power needs of the region, including the state's oil and gas industry. Early development work is underway on this project which we anticipate will be online in 2028.

• Repowering the coal-fueled Coleto Creek Power Plant near Goliad, Texas, set to retire in 2026 to comply with EPA rules, as a natural-gas-fueled plant with up to 600 MW of capacity.

• Completing upgrades at existing natural-gas-fueled plants that will add more than 500 MW of summer capacity and 100 MW of winter capacity.

In June 2026, Permian Power entered into a $583 million loan agreement with the Texas Energy Fund (TxEF) to finance the development of the 860 MW peaking plant in west Texas (TxEF Loan). The loan is non-recourse to Vistra, and interest on the TxEF Loan is calculated at a fixed rate of 3.0% per annum. As of June 30, 2026, $172 million was outstanding under the agreement.

Collateral Release

On December 2, 2025, S&P upgraded Vistra Operations' issuer credit rating from BB+ to BBB- and revised its outlook from Positive to Stable, and on March 20, 2026, S&P upgraded the Senior Unsecured Notes rating from BB+ to BBB-. On March 16, 2026, Fitch upgraded Vistra Operations' issuer default rating and the Senior Unsecured Notes rating from BB+ to BBB- and revised its outlook from Positive to Stable. As a result of these investment-grade ratings and the satisfaction of certain other conditions specified in the Vistra Operations Senior Secured Indenture, an investment-grade event was deemed to have occurred, and the liens on the collateral securing the Senior Secured Notes were automatically terminated and released in full on April 2, 2026 (Indenture Collateral Release).

VISTRA CORP.

Additionally, Vistra Operations repaid $2.444 billion in outstanding borrowings under the Term Loan B-3 facility in April 2026, and in coordination with the investment-grade ratings, met the collateral suspension provisions of the Vistra Operations Credit Agreement and Commodity-Linked Credit Agreement releasing all liens securing the Vistra Operations Credit Facilities and the Vistra Operations Commodity-Linked Credit Facility (Credit Facility Collateral Release). The Vistra Operations Credit Agreement and Vistra Operations Commodity-Linked Credit Facility were amended in June 2026 to, among other things, remove the collateral reinstatement requirements applicable to the Vistra Operations Credit Agreement and the Vistra Operations Commodity-Linked Credit Facility. The Vistra Operations Credit Agreement was also amended to release each guarantor from its guarantee to the extent related to the revolving credit loans, revolving credit commitments, letters of credit, letters of commitments and/or secured cash management agreements, in each case, under the Vistra Operations Credit Agreement. The Vistra Operations Commodity-Linked Credit Facility was amended to release each guarantor from its guarantee.

PJM Nuclear Power Purchase Agreements and Uprates

In January 2026, Vistra announced it had entered into 20-year PPAs with Meta, pursuant to which the Company has agreed to supply Meta with a total of 2,609 MW of carbon-free power and capacity from the Company's PJM nuclear power plants as follows:

• 1,268 MW of energy and capacity from Perry and 908 MW of energy and capacity from Davis-Besse; and

• 213 MW of uprate energy and capacity from Perry, 80 MW of uprate energy and capacity from Davis-Besse, and 140 MW of uprate energy and capacity from Beaver Valley.