The IEA projects that US data center power use will quadruple by 2035.
WASHINGTON — Electricity demand from American data centers is on track to more than quadruple over the next decade, the International Energy Agency said last week. The operator of the nation's largest power grid says the equipment needed to meet that demand isn't arriving fast enough.
In its annual World Energy Outlook, released Thursday, the Paris-based agency projects that U.S. data centers will use more than 830 terawatt-hours of electricity in 2035, up from about 200 terawatt-hours last year, under a scenario built on current U.S. policies.
That makes data centers the single largest driver of what the IEA describes as the first sustained rise in U.S. electricity demand since the early 2000s. Overall demand grows by about a quarter, or more than 1,000 terawatt-hours, over the same period, the agency said.
The IEA cautions that the pace of data center growth is highly uncertain, depending on how quickly artificial intelligence spreads and how efficient computing becomes.
But the agency also warns that the power system itself is becoming the bottleneck. Power plants, transmission lines, transformers and grid connections take far longer to build than the data centers they serve, it said, and shortages of equipment and parts are already slowing some projects.
**'Not Coming Online Fast Enough'**
PJM Interconnection, which operates the grid across all or parts of 13 states and the District of Columbia, said it is seeing the same thing.
"In as much as we have heard from developers, the industry in PJM's region is experiencing many of the same supply chain constraints seen across the electric industry," Jeff Shields, PJM's senior manager of external communications, told The Well News.
"Even after generation projects receive interconnection agreements, some are delayed by equipment shortages, manufacturing bottlenecks, permitting challenges and construction constraints," Shields said.
"As a result, new generation is not coming online fast enough to keep pace with rapidly growing demand, particularly from data centers," he added.
PJM's own numbers are steep. Its 2026 long-term load forecast projects demand from large customers, primarily data centers, growing from roughly 10 to 15 gigawatts today to about 30 gigawatts by 2030 and approximately 70 gigawatts by 2036.
Shields said the grid operator is nearly finished updating that forecast and should have a new number in 2027, "though I would not expect that to change much in order of magnitude."
The biggest share of that load is in Dominion Energy's territory in Virginia, followed by American Electric Power's, which spans Ohio, Virginia, West Virginia and Indiana, Shields said. PPL in Pennsylvania and ComEd in Illinois are emerging as secondary growth areas.
Northern Virginia appears on the IEA's map of the largest U.S. data center hubs, alongside places like Dallas-Fort Worth, Phoenix, Chicago and Columbus, Ohio.
**A Turbine Backlog**
In the IEA's projections, natural gas does much of the work of keeping up.
Gas-fired generation rises by almost 500 terawatt-hours through 2035, supplying nearly 45% of all the new power the country adds. Existing plants run more often, new ones connect to the grid, and developers build gas generators right alongside large data centers.
But orders for new gas turbines reached a 25-year high in 2025, the agency said, and the manufacturing backlog has stretched waits for the equipment.
Investment in gas-fired power was about $7 billion a year in 2022 and 2023. It hit $32 billion last year and is expected to top $50 billion a year before 2030, according to the report.
The IEA also expects nuclear power to grow after 2030, helped by federal tax credits and loan guarantees and by technology companies seeking reliable power for data centers. More than 40 gigawatts of small modular reactors are tied to announced purchase agreements, it said.
Because of federal measures keeping coal plants open that had been scheduled to close, coal-fired generation stays higher than the agency projected a year ago. It still falls by about a quarter by 2035.
**Who Pays for the Wires**
The biggest single cost may be the grid itself.
U.S. spending on power lines and related infrastructure climbed from $73 billion in 2020 to $118 billion in 2025, the IEA said. It is projected to average close to $140 billion a year over the next decade as utilities hook up new power plants and large customers, replace aging equipment and harden the system.
Part of that increase, the agency noted, reflects higher prices for transformers, cables and materials, and a shortage of skilled workers.
Who ends up paying for those upgrades is a growing question for regulators and households alike.
"Today, the transmission costs associated with serving new large loads are spread across several different planning and cost-allocation processes," Shields said. "Some costs are assigned directly to the customer causing them, while other costs can end up being allocated more broadly to transmission customers through local or regional transmission planning processes."
PJM filed a proposal with the Federal Energy Regulatory Commission on Nov. 16, which it calls the Fast Energization Process, that it says is meant to change that.
The proposal "is designed to identify the transmission upgrades needed to serve new large loads such as data centers so that the state-regulated utilities can choose to assign those costs to the customers driving them, rather than spreading those costs broadly across existing ratepayers," Shields said.
He noted that the decision would rest with the states and their utilities. "PJM does not have authority over cost allocation," he said.
Dominion Energy, whose Virginia territory holds the largest share of PJM's data center load, did not respond to a request for comment by deadline.
**'Make Them Pay You'**
The report landed a day before President Donald Trump, at a White House news conference, said his administration won't allow American companies to build data centers in other countries and will put "a tremendous tax" on those that try.
Trump urged communities to welcome the facilities and bargain for benefits.
"Make them pay you, make them pay your community, but take advantage. Don't shut them off," Trump said. He added that the companies are "going to build their own electricity, so the electricity is going to go down. Actually, your electricity costs will go down."
The IEA's projections don't address that claim directly, but they do show many developers building their own gas generation next to data centers. The Department of Energy did not respond to a request for comment on the IEA's projections.
**A Global Shock**
The data center findings are one part of a 564-page report dominated by the fallout from this year's disruption of oil and gas shipments through the Strait of Hormuz, which the IEA calls the largest energy supply shock in history.
"The Hormuz crisis has delivered a huge shock to the system," IEA Executive Director Fatih Birol said in a statement. "While the energy sector and the global economy have shown considerable resilience, the longer the crisis lasts, the deeper the effects will be. And I don't see any credible pathway for the energy world to return to the way it was before."
The agency said countries are responding by diversifying their supplies, leaning harder on energy they can produce at home and speeding up the shift to electricity. Birol cautioned that "in pursuit of greater energy security, countries must take care not to replace one dependency with another."
The IEA stresses that its scenarios are not forecasts.
For the United States, its projections show the country strengthening its position as the world's largest gas producer. By 2035, it overtakes Qatar as the world's largest gas exporter, with liquefied natural gas exports approaching 310 billion cubic meters a year.
But the report also warns that if the Middle East conflict is clearly resolved, a delayed wave of new LNG supply could hit the market at once, creating a buyer's market that pushes prices down.
The American Petroleum Institute, the oil and gas industry's largest trade group, said the report makes the case for more U.S. production.
"Amid an unprecedented global energy crisis, America's oil and natural gas industry continues to invest to meet growing demand at home and abroad," an API spokesperson said in a statement to The Well News.
"The IEA's latest outlook highlights the need for additional supplies, and increased U.S. production can help fill that projected gap, bolster our nation's energy security and deliver affordable energy for consumers," the spokesperson added.
The Solar Energy Industries Association and the Industrial Energy Consumers of America, which represents large manufacturers that rely on natural gas, did not respond to requests for comment by deadline.
Neither did the IEA's press office. The U.S. Energy Information Administratio