The Ohio Power Siting Board has approved the construction of a natural gas plant that will power an EdgeConneX data center in Pickaway County, Ohio.
The Ohio Capital Journal first reported the decision. The proposed data center had drawn criticism from local residents, who cited concerns about higher utility bills, noise pollution, and its environmental impact.
The Ashville Village Council initially approved the data center in April and also backed the development of the 800MW power plant, which is expected to serve the data center behind the meter. EdgeConneX agreed to provide up to $102 million to the local community to support the deal. Residents responded negatively and gathered enough signatures to force a referendum on whether to override the council's decision.
According to local reporting, 81 percent of Ashville voters opposed the agreement with EdgeConneX during the midterm elections. Despite the rejection, the Ohio Power Siting Board approved the project, stating that the developer had met a statutory requirement that the project is in the public interest. The regulator cited the project's potential economic benefits, the backing of the local council, and the developer's promises to limit noise during construction as key reasons for its decision.
The board acknowledged the Ashville community vote but said it has ultimate authority to issue the permit regardless of the outcome.
Project opponents have 30 days to request reconsideration of the ruling. If the Power Siting Board does not change its decision, opponents could appeal to the Ohio Supreme Court.
Founded in 2009, EdgeConneX operates or is developing more than 90 data centers across more than 50 markets in North America, Europe, Asia-Pacific, and South America. The company began with smaller-scale data centers in the US but has gradually expanded in scope and geography, moving into build-to-suit and hyperscale facilities.
EdgeConneX has increasingly turned to natural gas to power its expansion. In addition to the Ashville facility, the company has filed to build a 430MW natural gas-fired plant to power its planned data center in New Albany, Ohio, behind the meter.