Bright Horizon의 Cheyenne 유틸리티는 와이오밍주 내 Microsoft 데이터센터 3곳에 전력망 연결을 구축하기 위한 계약을 제출했다.
Cheyenne Light, the Wyoming utility owned by Bright Horizon Energy, filed agreements with the Federal Energy Regulatory Commission on Tuesday, Nov. 24, to build distribution and transmission infrastructure for three planned Microsoft data centers, Utility Dive reported [1]. The filed agreements are redacted, so their size and terms are not public [1].
Microsoft pays for the infrastructure through a contribution in aid of construction, an up-front payment by the customer [1]. Cheyenne Light says FERC does not have jurisdiction over the retail agreements and filed them "out of an abundance of caution," citing recent FERC statements on how utilities recover transmission costs for large loads [1]. It plans to serve the data centers under its existing Large Power Contract Service tariff [1].
Bright Horizon is the holding company formed when Black Hills Corp. and NorthWestern Energy Group completed their merger this month. MLQ.ai covered the close of the deal.
**The Google load and a 3 GW pipeline**
The Microsoft filings add to a larger build in Cheyenne. In its third-quarter 10-Q, Black Hills said a Google data center is expected to begin taking service in late 2027 and ramp to its projected peak load by the end of 2030 [2]. The utility expects to provide up to 590 MW of grid-connected service and to manage about 2.1 GW of third-party contracted resources through a privately managed microgrid [2]. To supply the 590 MW, it plans to invest about $1.8 billion in 564 MW of new gas generation between 2027 and 2029 through a non-regulated affiliate [2].
The company warned in the same filing that it "will have increased exposure to a single large customer" [2]. Utility Dive reported that Cheyenne Light is working through a 3 GW data center pipeline that includes 600 MW of combined Microsoft and Meta projects, and that the utility serves about 46,000 retail customers [1]. Its system set an all-time peak of 439 MW on July 20, 2026, up from 379 MW in June 2025 [2].
Cheyenne Light has also proposed a Large Customer Transmission Cost Adjustment Mechanism under which large-load customers would pay their share of transmission expansion. The utility plans to use it to recover $686 million for two transmission projects, and Wyoming regulators are expected to rule by mid-2027, according to Utility Dive [1].