Policy · Report
Texas will audit up to 300 projects, predominantly data centers, following Governor Greg Abbott’s executive order.
State-level regulatory scrutiny on grid interconnection queues could delay energization timelines and force developers to front-load transmission infrastructure costs.
Trade pressSlicast · August 21, 2026 · US · Source: Google News
importance 82State grid operator officials told the Public Utility Commission that the audit and verification of data centers ordered by Gov. Greg Abbott will involve about 250 to 300 projects, most of which are data centers.