TSMC의 텍사스 신고서에 따르면, 브라조스 카운티에 들어설 226억 달러 규모의 프로젝트는 2031년이 되어야 2나노미터 이하 칩을 생산할 수 있는 것으로 나타났다.
TSMC has applied for a new fab and campus near College Station in Brazos County, Texas. The proposed fab would sit one county over from Terafab, would likely share supply chains with it, and would be positioned to make 2nm-class chips by 2031. The $22.6 billion plan, detailed in an application under Texas's Jobs, Energy, Technology and Innovation (JETI) program for a school property-tax limit, shows how the Taiwanese chipmaker plans to expand its U.S. operations. The fab wouldn't make 2nm or more advanced chips until 2031, six years after 2nm volume production began in Taiwan. It would come with a school-tax break valued at around $354 million.
This would be the company's "second campus" for advanced chipmaking in the U.S. and the first outside Arizona. The Comptroller has recommended the tax application for approval, but the school district and the governor still have to grant it. The application comes from TSMC Arizona Corporation, TSMC's Phoenix-based subsidiary. Construction is projected to start in 2027, but the plan remains under evaluation, and nothing in the filing commits TSMC to buy the land or build on it.
TSMC is looking to build out more in the U.S. because most of its large customers are based there, and the government has been "very helpful" in pursuing additional fab capacity, Chairman and CEO C.C. Wei said in October. Texas is one option for expanding beyond Arizona, though the filing doesn't say what drew TSMC there. TSMC judges each site on its tax environment, workforce availability, utility capacity and cost, and site and infrastructure readiness, as well as its "long-term scalability and expansion potential." TSMC says Arizona offers "established operational efficiencies and lower capital risk," and that the tax incentive would help further.
TSMC has "nearly 20 fabs worldwide in progress," Wei said on the October earnings call, including 13 leading-edge and advanced packaging fabs in Taiwan and "another five to six fabs overseas." Annual capacity for its 2nm (N2) family is expected to more than double in 2027. TSMC also expects more of its fabs to ramp up in the U.S.
Texas wouldn't begin commercial operations until 2031, and the economic model filed with the plan doesn't have the site at full operations until 2032. By contrast, the second fab in Arizona is expected to begin volume production in Q3 2027, but at 3nm. N2 has been in high-volume production in Taiwan since Q4 2025. TSMC expects A14, its next full node after N2, to enter risk production in 2027 and volume production in 2028. By 2031, A14 is set to have been in volume production for about three years, so a Texas fab that starts on 2nm would be at least a generation behind TSMC's leading edge. Taiwan has also debated limits on how advanced TSMC's overseas fabs can be.
**TSMC's roadmap and the Texas timeline**
| Milestone | Where | When |
|---|---|---|
| 2nm (N2) volume production | Taiwan | Q4 2025 |
| A16 (a 2nm-family node) volume production | TSMC, site not stated | 2027 (expected) |
| 3nm volume production, second fab | Arizona | Q3 2027 |
| A14 volume production | TSMC, site not stated | 2028 |
| High-NA EUV adoption | TSMC, site not stated | 2030 (planned) |
| 2nm "and/or more advanced," commercial operations | Texas (proposed) | 2031 |
The new site would have one or more fabs, but as it stands, Brazos County's announcement describes one. For scale, we estimate that a single 2nm-class module with about 20,000 wafer starts a month costs $25 billion to $35 billion, so this plan's $22.6 billion budget falls below the low end of that range.
The price tag is split several ways. Buildings and other real property account for $8.60 billion, while tooling, machinery and equipment account for 62% of the total, or $14.02 billion. On the filing's list, that equipment category also covers power, HVAC, cleanroom, water and gas systems. Building spending would come first, in 2027, 2028 and 2029. Tool spending would begin in 2029, peak at $9.05 billion in 2030, with about 65% of the tool budget landing that year, and end at $963.9 million in 2032. The form's Schedule A stops at 2031 and shows a $21.66 billion total.
**TSMC's proposed Texas project: spending and hiring by year**
| Year | Buildings | Machinery and equipment | New hires |
|---|---|---|---|
| 2027 | $729.0 million | — | 0 |
| 2028 | $2.59 billion | — | 757 |
| 2029 | $5.28 billion | $649.2 million | 1,110 |
| 2030 | — | $9.05 billion | 232 |
| 2031 | — | $3.36 billion | 0 |
| 2032 | — | $963.9 million | 0 |
| **Total** | **$8.60 billion** | **$14.02 billion** | **2,099** |
The tool spending schedule lines up with a change in how TSMC prints its chips. Lithography, the step that uses light to project circuit patterns onto the wafer, requires advanced machines. The most advanced do this with extreme ultraviolet (EUV) light. High-NA EUV tools have a higher numerical aperture, which gathers more light to print finer features in one pass. Wei said TSMC intends to use High-NA in 2030, which matches the 2030 peak in Texas tool spending. That is a company-wide plan, however, and nothing in the Texas plan gives a delivery schedule or names High-NA tools specifically.
What the plan does spell out is its list of eligible property: fab and central utility plant buildings, cleanroom systems, ultra-pure water and wastewater treatment with water-reclaim systems, bulk and specialty gas, automated material handling, and gas-insulated switchgear.
The list also names mask or reticle shop equipment, as well as lithography, etch, deposition, implant, chemical mechanical planarization (CMP), diffusion, and clean/wet tools, by type. It names no tool vendors, EUV tool counts or wafer capacity. The mask shop is highlighted as "co-located within the fab and integral to the manufacturing process." Masks are patterned plates that a lithography tool uses to project patterns onto each wafer, one per chip layer, and every new design needs its own set. Making them on site suggests the fab is meant to stand on its own. Wei also said TSMC is working with ASML on a 12-inch photomask by 2031, the year the Texas site would open.
The site lies in Brazos County and spans 86 parcels and almost 3,232 acres, or about five square miles. For comparison, TSMC's Phoenix campus covers about 1,078 acres on the county tax roll, with about 902 more acres purchased in January. The Texas site would therefore be about 1.6 times that total. TSMC would build and manage the site, which sets it apart from Terafab, a fab being planned by a TSMC customer one county over. Wei has confirmed talks about using its capacity but said any such fab would have to be run by TSMC.
Residents in areas slated for fabs and data centers tend to raise two concerns, both related to utility usage. The first is power. A local report says Bryan Texas Utilities provides power to the proposed area, but it's unclear who would serve the fab. For scale, a utility filing in Arizona reportedly puts TSMC's built-out Phoenix campus at about 1.9 gigawatts, a figure for the whole campus rather than a single fab.
The second is water. Wellborn Special Utility District reportedly provides service, but the developer is said to intend to buy its water from a third party instead. As a comparison, a state document on an unnamed company's $45 billion, two-fab project in Sherman, as reported by the Dallas Business Journal, lists 8 to 10 million gallons a day to start, with a peak of 20 to 25 million after buildout. That is not a one-to-one comparison. The Sherman project is targeting production in Q4 2029.
Economic impacts are a major part of the deal. The plan projects 2,099 direct jobs by 2030, while the agreement would require only 35, the legal minimum. Pay is another matter: TSMC projects an average salary nearly double the wage level that would need to be met.
Texas appears willing to work with TSMC. Deputy Comptroller Noah Betz signed a recommendation for approval this week. The gross tax benefit would build over 14 years, starting four years before the formal incentive period, and would cut the district's maintenance and operations (M&O) levy on the project nearly in half. Even so, the full $354.1 million is only 1.6% of the $22.6 billion investment. In return, TSMC would have to post a performance bond equal to 10% of the benefit.
The Comptroller believes the incentive is a compelling factor and that TSMC would not invest in Texas without it. The office says it has not audited or verified the company's projections. TSMC, for its part, calls the limit "determinative."
**The Texas tax deal in numbers**
| Measure | Figure | Source |
|---|---|---|
| Direct jobs TSMC projects | 2,099 by 2030 | Application |
| Jobs the agreement would require | 35 | Comptroller |
| Average salary TSMC projects | $135,687 in 2028, rising 2% a year | Application |
| Minimum average wage for the project's jobs | $73,603 | Comptroller |
| Construction workers, 2027–2029 | 9,841 a year on average; 18,134 at the 2029 peak | Consultant's model |
| Out-of-town visitors | 708 a year; average stay 41 days | Consultant's model |
| Tax benefit, total | $354.1 million | Comptroller |
| Tax benefit during construction, 2028–2031 | $123.6 million | Comptroller |
| Tax benefit in the incentive period, 2032–2041 | $230.6 million | Comptroller |
| School M&O tax over 20 years, without the agreement | $759.3 million | Comptroller |
| School M&O tax over 20 years, with the agreement | $405.2 million | Comptroller |
| Performance bond | $35.4 million | Comptroller |
A potentially far larger incentive is federal: a tax credit worth 35 cents back on every qualifying dollar spent, as long as construction technically begins before the end of the year. "Qualified" means the cost of the fab's depreciable physical property that is integral to running the fab, meaning the buildings and tools, counted in the year each goes into service. "Construction" means actual physical work of a significant nature, or paying or incurring at least 5% of the qualifying property's cost, with work continuing afterward. Construction here is projected to start in 2027, after that cutoff. Off-site work under a binding written contract or early spending this year could still count, and an extension has been proposed in the Senate.
Land doesn't count toward the credit, and neither does office space. The credit also comes off the tax bill dollar for dollar rather than as a deduction. The rate was 25% under the 2022 CHIPS Act and rose to 35% for property placed in service after 2025. If the full $22.6 billion qualified, the credit would be worth about $7.9 billion, but not every dollar qualifies.
If Texas doesn't work out, TSMC is also considering "a new land parcel in Arizona," which would be closer to its existing North Phoenix site. TSMC says this could make many things easier, such as handling the workforce and logistics, and would allow it to use existing suppliers and relationships on known infrastructure.
The tax agreement needs approval from both the College Station ISD board and the governor. The district also owns one of the parcels on TSMC's list for the site: almost 91 acres, including a 24,496-square-foot building from 2024. The board has set a public hearing for Dec. 10, with public comment, and could approve the project's reinvestment zone that day. The district has 30 days from receiving the application, which puts its deadline in late December. Town halls in Brazos County could reportedly begin as early as the first week of December, though the county has promised only one, "in the near future."
Assuming the project moves forward, the real measure begins with the first phase on land. Even if production arrives a generation late, it would be a positive development for U.S.-based chipmaking.