The Indiana Utility Regulatory Commission (IURC) approved AES Indiana's $1.3bn plan for solar, storage and transmission to serve Google's data center in Monrovia, with Google expected to pay all associated costs.

The approval gives a hyperscale campus dedicated renewable-plus-storage supply and transmission build, and the customer-funded cost structure offers a template for serving large AI loads without shifting costs to other ratepayers.
Trade pressSlicast · October 14, 2026 at 14:09 UTC · Global · Source: Data Center Dynamics
importance 70
Read the original