A proposed Alberta data center could support up to 800 construction jobs, while Jet.AI has invested $1.75 million in its developer.
Jet.AI (Nasdaq: JTAI) reported third-quarter 2026 revenue of $730,962 while its net loss widened from the prior-year quarter. Revenue compared with $591,614 a year earlier, and the net loss reached $5,915,308, versus $1,966,049. Cash was $3,263,542 at September 30, while nine-month operating cash use increased to $11,459,615 from $8,917,202.
Jet.AI completed its flyExclusive transaction on July 13, 2026. Final consideration totaled 7,221,468 flyExclusive shares. A $1.75 million StratGrid investment provides approximately 15% ownership and an approximate 15% economic interest in the planned Wheatland project, which targets up to 240 MW. Regulatory approval remains pending. Manitoba development has slowed, while Jet.AI expects Moapa's power study before year-end. Discussions under an earlier non-binding transaction proposal ended, and Jet.AI is evaluating alternatives. Its AIIA sponsor interest was worth approximately $17.5 million at September 30.
The filing also reports the following:
- Third-quarter gross profit increased to $209,915 from $91,374 in 2025.
- Nine-month revenue increased to $5,563,487 from $2,551,369 in 2025.
- Nine-month gross loss of $120,115 replaced gross profit of $616,838 in 2025.
- Third-quarter sales and marketing expense fell to $64,643 from $103,469 in 2025, while nine-month sales and marketing expense rose to $480,938 from $232,736 in 2025.
- Third-quarter net loss widened to $5,915,308 from $1,966,049 in 2025. Nine-month net loss widened to $10,873,081 from $7,520,876 in 2025.
- Continuing-operations net losses widened to $5,704,498 for the quarter and $9,534,727 year-to-date, versus $1,055,663 and $4,275,875 in 2025.
- Discontinued-operations losses narrowed to $210,810 for the quarter and $1,338,354 year-to-date, versus $910,386 and $3,245,001 in 2025.
- General and administrative expenses rose to $5,669,592 for the quarter and $9,249,417 year-to-date, versus $1,074,389 and $4,637,201 in 2025.
- Research and development expenses rose to $59,954 for the quarter and $214,518 year-to-date, versus $39,327 and $189,295 in 2025.
- Operating losses widened to $5,584,274 for the quarter and $10,064,988 year-to-date, versus $1,125,811 and $4,442,394 in 2025.
- Third-quarter unrealized investment loss was $167,000, versus none in 2025. Nine-month unrealized investment gain was $326,000, versus none in 2025.
- Cash and cash equivalents rose to $3,263,542 at September 30, 2026, from zero at December 31, 2025.
- Current liabilities fell to $1,108,972 from $3,709,069 at December 31, 2025.
- Stockholders' equity rose to $26,335,943 from $21,975,007 at December 31, 2025.
- Common shares outstanding increased to 3,581,386 at September 30, 2026, from 31,413 at December 31, 2025.
- Wheatland construction could start in the second half of 2027, with operations potentially beginning in the fourth quarter of 2028, subject to approvals and milestones. StratGrid has begun stakeholder consultation, and it anticipates applying to the Alberta Utilities Commission in the first quarter of 2027.
- Moapa's planned 50-megawatt campus remains on schedule. Its preparatory work depends on third parties, including consultants and utility providers.
- Manitoba policy challenges slowed development. Jet.AI and Consensus Core are evaluating a smaller initial scale.
- Alternative strategic transactions remain under evaluation, with an investment bank retained. No definitive replacement transaction has been agreed.