영국 업계에 350억 파운드 규모의 소형 원자로 프로그램 제안이 브리핑되었다.

만약 자금이 확보된다면, 350억 파운드 규모의 소형 원자로 프로그램은 향후 AI 데이터센터 전력 수요를 감당할 국내 청정 전력 옵션을 만들어낼 수 있으나, 실제 배치까지는 여전히 오랜 시간이 걸릴 전망이다.
업계 전문지Slicast · 2026년 11월 26일 10:41 UTC · 미국 · 출처: New Civil Engineer
중요도 55

More than 200 British companies have attended a Birmingham event to discuss potential roles in a proposed £35bn programme to build 14 small modular nuclear reactors across three UK sites.

The proposal, put forward by SGE SMR UK in July, would use BWRX-300 reactors and provide about 4.2 gigawatts of generating capacity. The company says this would be equivalent to roughly 11% of current UK electricity consumption, or enough to supply eight million homes. It is targeting first power in 2034 and estimates the reactors could operate for 60 to 80 years.

The proposal is being considered under the Government's Advanced Nuclear Framework and has progressed to a preliminary regulatory assessment stage. It has not yet received approval to proceed with construction.

The 24 November meeting was jointly hosted by SGE SMR UK, GE Vernova Hitachi Nuclear Energy and Samsung C&T. Discussions covered what British businesses might be able to provide for the programme, including engineering, manufacturing, construction, electrical systems, logistics and long-term maintenance. The organisers said suppliers would be able to register their interest in joining the prospective supply chain.

The companies are planning a standardised approach in which successive projects use the same reactor design and delivery framework. They say this could make repeated construction more efficient, although the programme's costs, timetable and eventual contribution from UK suppliers remain to be established.

SGE SMR UK chief executive Rafał Kasprów said the company aimed to develop a fleet rather than build individual reactors. GE Vernova Hitachi and Samsung C&T said early engagement with suppliers would help identify the capabilities needed for future projects.

Kasprów said: "Our ambition is not simply to build individual reactors, but to establish a fleet programme that can be delivered repeatedly and efficiently in the UK. British industry has a critical role to play in making that possible. The UK has a highly skilled workforce and a strong industrial and nuclear heritage. Our ongoing engagement with suppliers across the country is helping to shape the detail of our UK supplier strategy and identify how British businesses can contribute to fleet delivery at scale, ensuring that investment in new nuclear creates opportunities throughout the UK supply chain.

"Standardisation, repetition and a fleet-based approach are fundamental to our plans for the BWRX-300. Building a strong domestic supply chain alongside that model will be equally important as we work to turn our proposal into a major British infrastructure and industrial programme."

Samsung C&T senior vice president Jung Kim added: "Delivering an SMR fleet at scale requires disciplined project execution and a strong local supply chain from the outset. Drawing on our extensive nuclear construction experience, including the Barakah Nuclear Power Plant in the UAE, Samsung C&T looks forward to working alongside SGE SMR UK, GE Vernova Hitachi Nuclear Energy and British industry to explore an efficient and repeatable delivery model that supports the UK's long-term nuclear ambitions."

The BWRX-300 is a 300-megawatt boiling water reactor. The first unit is under construction at Ontario Power Generation's Darlington site in Canada. The UK programme's proposed 14 reactors would be spread across three sites, which have not been named in the announcement.

SGE SMR UK said it expected to open a UK office with local staff by the end of 2026. It plans to finalise its supply and delivery strategy in 2027.