Applied Digital Reports Fiscal First Quarter 2027 Results
DALLAS, Oct. 07, 2026 (GLOBE NEWSWIRE) -- Applied Digital Corporation (Nasdaq: APLD) ("Applied Digital" or the “Company") , a U.S. based designer, developer, owner, and operator of large-scale, purpose-built data centers engineered to support high-performance computing (“HPC”) workloads, including artificial intelligence (“AI”), machine learning, and other accelerated-compute applications, reported financial results for the fiscal first quarter ended August 31, 2026.
ChronoScale Holdings Corporation ("ChronoScale"), the Company’s majority-owned accelerated-compute platform, is a public company which owns and operates our historic cloud services business and its results are consolidated into our financial statements, but excluded in the non-GAAP financial measures set forth below. Unless otherwise specified, disclosures in this earnings release, including the below, reflect continuing operations only.
Fiscal First Quarter 2027 Financial Highlights
Revenues: $341.9 million, up 322% from the prior year comparable period
Net loss attributable to common stockholders : $221.0 million
Net loss attributable to common stockholders per basic and diluted share: $0.76
Adjusted revenue: $300.4 million
Adjusted net loss: $4.1 million
Adjusted net loss per diluted share : $0.01
Adjusted EBITDA: $64.4 million
Net Operating Income: $58.8 million
Adjusted revenue, Adjusted net income (loss) , Adjusted net income (loss) per diluted share , Adjusted EBITDA, and Net Operating Income are non-GAAP measures. A reconciliation of each of these Non-GAAP Measures to the most directly comparable financial measure presented in accordance with accounting principles generally accepted in the United States (“GAAP”) is set forth below. These non-GAAP measures exclude the results of ChronoScale. See “ Reconciliation of GAAP to Non-GAAP Measures. ”
Recent Highlights
As previously announced on June 8, 2026, signed a 210 MW, 15-year lease at Delta Forge 2 with the Company’s tier-one investment grade hyperscaler customer, representing approximately $5.2 billion of base-term contracted revenue.
Delivered Phase 1 of Building 2 (75 MW) at Polaris Forge 1 Ready for Service on July 1, 2026, bringing total live capacity at the campus to 175 MW.
Closed $1.59 billion of 7.000% Senior Secured Notes due 2031, issued at par through subsidiary APLD ComputeCo 3 LLC, to fund construction of the third HPC building (150 MW) at Polaris Forge 1 and to repay the $300 million bridge facility.
ChronoScale announced plans with Microsoft for a 50 MW AI compute deployment in North America featuring NVIDIA GB300 NVL72 systems and liquid cooling.
Subsequent to the Quarter
Delivered the second 75 MW phase of Building 2 at Polaris Forge 1 Ready for Service, bringing total live capacity at the campus to 250 MW.
Secured up to approximately 1 GW of potential power capacity in Finland, establishing a strategic foothold in an emerging European AI market.
Entered into a Power Purchase Agreement with Base Electron, for the purchase of capacity and energy from an approximately 1,200 MW natural gas-fired generation facility to be developed by Base Electron in North Dakota.
Polaris Forge 1 was named Project of the Year by the Mid-America Economic Development Council, recognizing its economic impact, community investment, partnerships, and technological innovation.
Through Applied Digital Cares, committed $350,000 in grants across five organizations in Oliver County, North Dakota, home to Polaris Forge 3, supporting first responders, schools, and community facilities.
Management Commentary
“Our goal is to establish Applied Digital as the category leader in the design, construction, deployment, and operation of purpose-built AI factories,” said Wes Cummins, Chairman and Chief Executive Officer of Applied Digital. “We are building for the long term, with a clear focus on developing large-scale, sustainable AI factory campuses and securing durable, high-quality, long-term contracts with proven, tier-one, investment grade hyperscalers that are leaders in the AI industry.”
On October 1, 2026, the Company achieved Ready for Service for the second 75 MW phase of Building 2 at Polaris Forge 1, bringing fully operational critical IT load at the campus to 250 MW across two buildings and 10 data halls. The Company expects initial operations at Polaris Forge 2 in Harwood to increase delivered critical IT load across our North Dakota campuses to 300 MW by the end of calendar 2026, further demonstrating the Company's ability to execute against its development pipeline.
The Company also took its first step outside the United States, signing an agreement for up to approximately 1 GW of potential power capacity in Finland. Finland shares many of the characteristics that made North Dakota a compelling location for the Company's AI factories: a cool climate that supports efficient operations, access to abundant and reliable power, and room to scale. Management believes this agreement offers meaningful long-term potential while limiting the Company's initial exposure. While Applied Digital's near-term development strategy and execution priorities remain firmly centered on its growing U.S. portfolio, Finland presented itself to us as a measured, opportunistic step into a market that offers attractive long-term potential.
North Dakota remains central to the Company’s strategy. The Company believes the state’s low-cost power, abundant energy resources, low population density, and climate make it one of the most compelling locations in North America for AI factory development, and management expects additional hyperscalers to enter the Dakotas over time. As coastal and metro markets become increasingly constrained and more expensive, Applied Digital believes campuses in low-cost, power-rich regions can support stronger long-term terminal values and become more difficult to replicate.