ICE has launched a tool that scores the risk of US data center projects being delayed or halted.

A quantified schedule-risk score gives lenders, developers and utilities a common way to price delay risk on US data center pipelines, which could shape financing terms.
업계 전문지Slicast · 2026년 11월 17일 18:36 UTC · 중동 · 출처: MLQ.ai
중요도 42

Intercontinental Exchange, the owner of the New York Stock Exchange, on Tuesday launched a tool that estimates the risk that a US data center project is delayed or halted before it is built [1] [2]. ICE is pitching the ICE Data Center Site Analytics Tool to developers, investors, lenders and municipalities that want to judge a site's feasibility before committing capital [1].

The core of the product is the ICE Data Center Construction Disruption Model, which ICE says was trained on thousands of US data center permitting and project outcomes. It estimates the probability that construction runs into disruption within 24 months, and achieved 77% accuracy when tested against historical permit outcomes, the company said [1]. ICE has not published the test details, and the accuracy figure has not been independently checked.

The tool covers more than 3,100 US counties and tracks thousands of existing data centers across 47 geospatial data layers [1]. ICE groups the model's inputs into three buckets [1]:

- County permit history: past delay and stoppage rates, filing volume and trends, project value and fees.

- Local site characteristics: nearby electricity and water costs, plus census-tract education, broadband, poverty and unemployment levels.

- Market conditions: the ICE U.S. Mortgage Rate Lock Index at the time a permit was filed.

"Data center capital is moving faster than local permitting and community consensus, and that gap is now a material financial risk," said Larry Lawrence, head of ICE's Geospatial Intelligence team. "On a median-sized $2.7 billion project, a 12-month delay can cost $162 million to $270 million" [1]. The product sits inside ICE Geospatial Intelligence, which links location data to securities and covers more than 50,000 municipal bond issuers [1].

Reuters tied the launch to rising political pressure on the industry after this month's midterm elections gave Democrats control of both chambers of Congress. It noted that some Democrats, including Representative Alexandria Ocasio-Cortez, have proposed pausing new data center construction until Congress adopts safeguards on utility costs, the environment and community oversight [2]. Republican Senator Josh Hawley has also backed a nationwide moratorium.

Local opposition is already stopping projects. Prologis is suing Trenton, Ohio after voters approved a ban on its 250 MW Amazon data center. On the grid side, PJM this week asked FERC to cut its interconnection studies for data centers to about a year. ICE did not say what the tool costs.