CDC has expanded its Western Sydney data centre proposal almost tenfold to 1.4GW.

A 1.4GW campus would make CDC one of the largest planned data-centre footprints in Australia, but it also magnifies grid-connection, power-supply and local planning hurdles in Western Sydney.
Trade pressSlicast · November 15, 2026 at 15:18 UTC · US · Source: Mingtiandi
importance 72

CDC Data Centres, backed by Infratil and Australia's Future Fund, has asked New South Wales planners to rewrite the environmental assessment requirements for its Kemps Creek site in western Sydney to cover a 1.4-gigawatt campus. That is almost 10 times the single-building proposal it filed in July.

In a scoping report addendum posted to the state's major projects portal in late October, CDC set out a campus on a 117.47-hectare (290-acre) site at 845-901 Mamre Road. The original proposal was for a single four-storey data centre drawing 144MW.

The 1.4GW figure is the campus's peak design capacity, including up to 1GW of IT load. It would make the CDC project larger than a 1.2GW campus proposed at 706-752 Mamre Road in Kemps Creek. That project, which has been linked to Sydney-based AirTrunk, is on track to become the first in Australia to pass 1GW.

The addendum comes six months after CDC signed a record 555MW contract with an unnamed US customer. That deal more than doubled its contracted capacity to over 1GW, with delivery across campuses already under development.

## Campus Expansion

The campus would comprise six two-storey data centres ranging from 120MW to 240MW of IT capacity, totaling 1.008GW, along with a power substation. The expansion adds a 29.14-hectare lot at the northern end of the site, bringing it to about 117.47 hectares (290 acres). CDC has also cut the project's proposed building height. In an August letter to CDC, the planning department urged the company to give strong consideration to bringing the project into line with the precinct's 20-metre height control. The revised design reduces maximum height from 35.2 metres to 25.5 metres, which is still above the limit. The environmental impact statement will have to address this.

CDC said consolidating the campus into a single filing responds to Penrith City Council's stated preference for a comprehensive plan covering the whole Kemps Creek site.

Power is the key dependency. The campus would need a high-voltage connection to the Transgrid network via an on-site switching station and substation. CDC has asked that the assessment requirements specifically cover grid connection details and the staging of electricity supply. The filing does not disclose an estimated development cost or completion timeline.

## Sydney Pipeline Swells

CDC is 49.7 percent owned by Wellington-based Infratil, 34.5 percent by the Future Fund and 12 percent by the Commonwealth Superannuation Corporation, with management holding 3.7 percent.

In May, the company outlined a 2.9GW pipeline comprising 671MW operating, 572MW under construction and 1.66GW of future capacity through fiscal 2034. Sydney accounts for 921MW of that future build, a figure that the Kemps Creek campus's IT load alone would exceed. The operator's existing Sydney footprint includes its Eastern Creek campus and Marsden Park, an A$3.1 billion, 504MW project approved by NSW last year.

## Mamre Road Cluster

CDC's plan adds to a cluster of large proposals along the Mamre Road industrial corridor, including the 1.2GW project linked to AirTrunk.

After the project's exhibition in March and April, the applicant, Plan Project Management, sought to amend the scheme. The amendment consolidates the campus into three buildings from six and cuts maximum height to 27 metres from 40 metres, while total power consumption stays at 1.2GW. The estimated development cost falls to about A$7 billion from roughly A$9 billion. The amended application had moved into the assessment phase as of 21 October.

The project has drawn 79 public submissions, many objecting to diesel generators, noise and the combined effect of several data centres on the same road.

Stockland is also advancing a 168MW facility at Kemps Creek with Fife Capital, while Microsoft is building its own campus in the area. Stockland and its partner John Boyd Properties recently dropped a data centre from their plans for the former Kogarah Golf Club near Sydney Airport.

Goodman Group earlier this year withdrew an application to build a data centre in the Sydney suburb of Lane Cove West, citing shifting government policy and opposition from local residents. AirTrunk has also abandoned plans to build a 140MW data centre in the same suburb.