OpenAI Signs Lease with SB Energy for 8GW Ohio Supercampus; Construction Officially Begins This Month
ATHENS, Ohio (WOUB) — OpenAI plans to lease most of a proposed data center campus in Pike County that could be one of the largest in the nation.
The U.S.-based artificial intelligence company also announced it will invest $40 million in a community grant fund to support local projects.
SB Energy, a subsidiary of the Japanese conglomerate SoftBank, announced in March plans to build a 10-gigawatt data center campus on the site of a former uranium enrichment plant just south of Piketon. The land is owned by the federal government. But it is unclear whether the data centers OpenAI plans to lease, at least initially, will be built on that site, which has been undergoing an extensive cleanup after decades of radioactive and other contamination.
For now, permit filings by SB Energy suggest it plans to build a large network of data centers on several parcels of private property in the area around the plant site. Applications submitted by SB Energy to the Ohio EPA for a permit to fill certain streams and wetlands during construction identify a little over 1,000 acres of private land where multiple data centers would be built, along with associated infrastructure, including power plants. SB Energy has already secured options from the landowners to purchase the property. The company notes in its latest application that it plans to begin construction in October.
OpenAI said in its announcement Monday that it has agreed to lease about 8 gigawatts of the proposed campus as it is built out. SB Energy will build, own and operate the data centers under a 20-year lease to OpenAI, according to the announcement. The centers will host NVIDIA AI hardware and software infrastructure. NVIDIA, meanwhile, will invest $1.5 billion in SB Energy and provide credit support for the land, power and buildout.
OpenAI says the project is expected to create 35,000 construction jobs during a six-year buildout through 2032, as well as 2,500 long-term operating jobs. OpenAI said it and SB Energy "will work to prioritize local workers, contractors, suppliers, trades, and service providers." It plans to work with unions, schools, workforce groups and other organizations to help residents prepare for construction, technical and operating roles.
According to OpenAI, the project is expected to generate hundreds of millions of dollars in state and local tax revenue over its lifetime. That revenue will primarily support schools, but also roads, emergency services, healthcare and workforce development.
Data center developments are facing growing opposition in Ohio and across the country. The centers use considerable electricity to power and cool racks of servers. Opponents often raise concerns about increased burdens on the electrical grid that could lead to expensive upgrades and higher costs for ratepayers. Another common concern is the significant amount of water data centers can use for cooling, depending on the type of system used.
OpenAI said in its announcement that SB Energy will pay the full cost of grid upgrades and new transmission lines needed to serve the Pike County data centers, and that these costs will not be shifted to ratepayers. The first 800 megawatts of the project are expected to be ready in 2028 and will be powered primarily by the existing energy grid, OpenAI said. Beyond that, new power plants and transmission lines connecting them to the grid will be built to support additional capacity. SB Energy has announced plans to invest $33 billion to build more than 9 gigawatts of natural gas generation and spend more than $4 billion on transmission lines to move that power across the grid.
According to OpenAI, the data centers will use a closed-loop, air-cooled system that recirculates water for cooling, rather than cooling towers that continuously consume water. Once the system is filled, "ongoing water use is expected to be comparable to an office building supporting a similar number of people, including sinks and restrooms, equipment washdown and maintenance, and landscaping," the company said in its announcement. OpenAI said it will fund new water infrastructure "in partnership with and to the benefit of local communities," and that once the site design is finalized, it will publicly report the project's expected water use.
The $40 million community investment OpenAI is pledging comes on top of a similar $40 million investment SB Energy has also made. OpenAI said how its $40 million will be spent "will be shaped by local residents' priorities such as schools, public safety, health care, utilities, workforce training, housing, veterans' services, small businesses, and support for working families."
OpenAI says it will publish an annual report detailing its progress on its many commitments, including local hiring, water and energy use, and community investment.
"We will continue to meet with residents, local officials, schools, businesses, labor organizations, and community groups to help shape an Ohio Community Compact," the company said. "The Compact will reflect local priorities and turn these principles into specific, public measures as the project moves forward."