Power approval set to delay Oracle's Wisconsin AI datacenter
Oracle's Wisconsin AI datacenter could miss its planned 2027 start date because the transmission infrastructure required to power it awaits regulatory approval. Research company Aterio warns that Project Lighthouse, being developed by Vantage in Port Washington with Oracle as tenant, faces a real risk of slipping beyond Oracle's target of delivering capacity to customers in the second half of 2027.
The timing concerns extend beyond Wisconsin. Oracle reportedly sent a force majeure notice to a Blue Owl Capital subsidiary developing Project Jupiter in New Mexico, seeking to defer payments if the campus failed to come online as planned rather than withdraw entirely. Oracle says that project remains on schedule.
Aterio stated: "The regulatory record points to the potential for dates later than company guidance, and Oracle's stretched finances, together with its force majeure notice on Project Jupiter in New Mexico this week, raise the potential for slippage on its largest campuses."
The immediate obstacle is American Transmission Company's (ATC) application to the Public Service Commission of Wisconsin (PSC) for approval to build the campus's grid connection. ATC is planning more than $2 billion in transmission infrastructure projects tied to datacenter developments across Wisconsin, ranging from high-voltage power lines and substations to upgrades of existing facilities. Construction requires PSC approval.
"The problem is power," Aterio said. "The campus cannot run until ATC connects it to the grid, and ATC cannot start building until the PSC approves its application."
The PSC closed the original case after withdrawing its finding that ATC's application was complete. ATC refiled in September, restarting the approval process.
Aterio's earliest scenario puts partial power in October 2027 and full supply in August 2028, though it considers that timetable highly unlikely. Its base case projects partial power in December 2027 and full supply in October 2028. An extended regulatory review could push those dates to June 2028 and April 2029. Even December 2027 power delivery would leave little room for testing and commissioning before Oracle's deadline.
A datacenter does not enter service as soon as first grid power arrives. Each building's electrical and cooling systems must be energized, tested and commissioned before carrying customer load. "We therefore expect the campus's load to ramp up mainly from the first quarter of 2028," Aterio said.
The Wisconsin delays come as the Financial Times reported that Tencent signed a $7 billion deal to lease around 100,000 AI processors from Oracle. For context, Oracle reported $55.7 billion in total capital expenditures for its fiscal 2026, which closed at the end of May, against total revenue of $67.4 billion. Capex guidance for the 2027 financial year is up to $95 billion.