A construction lien was filed against xAI's Colossus data-center facility in Memphis, signaling potential payment disputes or contractor issues during project build-out.

Construction delays or financing friction at Colossus may impact the project's energization timeline; important for tracking Musk-backed AI infrastructure capacity ramp.
Trade pressSlicast · September 23, 2026 at 12:19 UTC · US · Source: Action News 5
importance 45

Ferguson Enterprises LLC, a Virginia-based construction company, has filed a lien against MZX Tech LLC, a SpaceX subsidiary, claiming it is owed $4.2 million for work performed at the Colossus 2 data center in Whitehaven on Tulane Road. The company provided pipes, pipe valves, and fittings for the project.

This marks the ninth construction company to file a lien against one of Elon Musk's data centers, alleging non-payment for contracted work.