SOAR AI의 Ohio AI Compute Campus는 12월 31일 가동 개시 일정을 유지하고 있으며, 계약 매출은 2027년 1월부터 발생할 것으로 예상됩니다.

12월 31일 가동 목표와 2027년 1월 매출 개시 시점은 투자자들에게 새 오하이오 AI 컴퓨팅 캠퍼스와 관련한 구체적인 이정표를 제시한다.
업계 전문지Slicast · 2026년 10월 20일 12:05 UTC · 미국 · 출처: Yahoo Finance Australia
중요도 60

NORTH CANTON, Ohio, October 20, 2026: SOAR AI, Inc. (NYSE American: SOAR), formerly known as Volato Group, Inc. ("SOAR AI" or the "Company"), today provided a construction update on its AI compute campus in Chillicothe, Ohio. Low-voltage data hall transformers and cooling plant equipment are being installed this week, and the Company remains on schedule to place its first 4,096 AMD Instinct™ MI355X GPUs in service on December 31, 2026, with customer revenue expected to begin in January 2027.

The data hall, located at a former paper mill, is being converted into an AI facility with closed-loop liquid cooling. Following the MI355X deployment, the Company intends to deploy 4,032 next-generation AMD Instinct™ MI455X GPUs on the AMD Helios™ rack-scale platform. The data hall is expected to be ready to accept them in February 2027, with a contractual in-service date of June 30, 2027. The campus currently has 154 megawatts of power available and a roadmap to 480 megawatts.

**Approximately $1.2 billion under contract**

The GPU deployment is supported by a master services agreement and two four-year, take-or-pay orders representing $1.17 billion in aggregate contract value. The MI355X GPUs and the first 4,032 MI455X GPUs are planned to fulfill these orders, giving the Company long-term revenue visibility. Revenue under the first order is expected to begin in January 2027, subject to delivery and acceptance. Based on the contracted rates and anticipated service start dates, the Company expects these orders to generate approximately $175 million to $200 million in revenue in 2027.

**Construction progress**

Installation of the data hall's power and cooling equipment is underway:

- The substation, medium-voltage distribution and turbine backup power systems are active and commissioned.

- Low-voltage data hall transformers are being installed this week.

- Cooling plant equipment is on site and being installed now.

- Piping, wiring and other materials for the data hall have arrived on schedule.

**Milestones ahead**

| Milestone | Target |

|---|---|

| 4,096 AMD Instinct™ MI355X GPUs in service | December 31, 2026 |

| Contracted customer revenue begins | January 2027 |

| Data hall ready to accept 4,032 AMD Instinct™ MI455X GPUs on AMD Helios™ | February 2027 |

| 4,032 MI455X GPUs in service (contractual date) | June 30, 2027 |

| Up to two additional tranches of 4,032 MI455X GPUs each, for future customers | Second half of 2027, subject to financing and customer contracts |

*This is a paid press release. Contact the press release distributor directly with any enquiries.*