Fluidstack가 데이터센터로 전환하기 위해 Prologis 창고를 1억 6,290만 달러에 매입했다.

AI 컴퓨팅 개발사들이 기존 산업용 건물을 빠르게 전환할 수 있는 용량으로 인수하고 있음을 이번 거래가 보여주며, Prologis가 부동산을 공급하고 있다.
업계 전문지Slicast · 2026년 11월 26일 15:14 UTC · 미국 · 출처: MLQ.ai
중요도 72

Fluidstack has bought a 1 million square foot warehouse in Pennsylvania's Lehigh Valley from Prologis for $162.9 million, Commercial Property Executive reported on Thursday, Nov. 26, citing Yardi Matrix data. The price works out to about $161 per square foot, according to the publication. Neither company has announced the deal, and the sale date was not disclosed.

The property, Lehigh Valley East 16, sits on 85 acres at 2500 Liberty Drive near State Route 329 in Allen Township, Northampton County, and was completed in 2023. Prologis applied earlier this year to convert it into a hyperscale data center, and the Allen Township Board of Supervisors approved the plan unanimously in March.

**The conversion plan**

The plans repurpose the existing building and its truck parking into a data center of about 300 megawatts, with power from PPL Electric Utilities, a substation and closed-loop systems, according to Commercial Property Executive. The warehouse has 40-foot clear heights and about 5,990 square feet of office space. It sits about six miles from Lehigh Valley International Airport, near FedEx, DHL, Amazon and Aldi facilities.

When the Lehigh Valley Planning Commission reviewed the project in April, its staff asked for details on water and electricity use, cooling and emergency response, Lehigh Valley Public Media reported. "This looks to be the first data center that might actually come to fruition in the Lehigh Valley," Commissioner Christopher Amato said at the time.

Fluidstack is building data centers in Texas and New York under Anthropic's $50 billion US infrastructure plan, announced in November 2025. On Nov. 25, it launched Blackbird, a modular data center design that it says scales to 400 MW and can be built within six months (see MLQ coverage). Prologis has been converting more logistics sites into data centers. In Ohio, it is suing the city of Trenton to keep building a 250 MW Amazon Web Services campus after voters approved a ban (see MLQ coverage).

*Disclosure: MLQ.ai's newsroom uses AI tools, including Anthropic's Claude, to help produce its coverage.*