ICF says PJM's revised data center backstop procurement could be as little as 630 MW, down from an initial 6,800-MW target, reducing utility risks.

Cutting the backstop from 6,800 MW to as little as 630 MW materially reduces the procurement burden that PJM utilities would carry for data center load.
Trade pressSlicast · November 3, 2026 at 13:00 UTC · Global · Source: Utility Dive
importance 70

The PJM Interconnection on Thursday filed a revised reliability backstop procurement (RBP) proposal with federal regulators. The grid operator aims to begin the process on March 1, about seven months later than originally planned.

The revisions follow the Federal Energy Regulatory Commission's late-September rejection of most of PJM's initial proposal, which was designed to fill a capacity shortfall driven by data center development. FERC said the original plan's provisions for cost allocation, transmission owner exit rules and load-serving entity (LSE) collateral requirements may have been unjust and unreasonable.

PJM said in its recent filing that the proposed revisions were "carefully tailored" to address the issues FERC identified while keeping the RBP's fundamental structure and policy objectives intact.

Under the new proposal, "PJM is using more current information on large-load growth to improve cost causation, revising the collateral methodology, and, importantly, recognizing that an RBP obligation and its associated collateral can move with the load-serving obligation when a large customer changes LSEs," Maria Scheller, vice president of energy and planning at the consulting firm ICF International, said in an email to Utility Dive.

According to Scheller, the proposal sharply reduces risks for providers of last resort and default service providers, the utilities that supply power to customers who do not buy electricity from power marketers.

"If a large load initially relies on default service, the [provider of last resort] may temporarily carry significant RBP collateral and liquidity requirements," she said. "The key credit question is whether state rules provide timely, certain recovery and adequate customer security, so the utility remains an administrative intermediary rather than taking meaningful balance-sheet or stranded-cost risk."

As a result, the state role is especially important to the process's outcome, and some state utility regulators may need to craft new rules, Scheller said.

"Regulators may need to determine customer-specific allocation, establish appropriate security and cost-recovery rules, track changes in suppliers, and decide what happens if the underlying large load shrinks, defaults or disappears," she said.

The proposal reduces the direct risk to residential and other existing customers but does not eliminate it, according to Scheller.

"Administrative costs, collateral and financing costs, regulatory lag, customer default and stranded-cost risk can still create indirect exposure if the state-level mechanisms do not keep the obligation tightly attached to the large load that caused it," she said.

The planned procurement aims to fill a 6.8-GW capacity shortfall from PJM's 2028/29 base residual auction. However, the procurement may shrink significantly from that initial target after PJM recalculates how much capacity is needed, according to equity analysts at Jefferies.

The analysts said in an Oct. 28 note that PJM utilities, including PPL Electric, FirstEnergy and AES Ohio, recently lowered their overall near-term large load forecasts by 6.5 GW, citing recent filings to PJM's Load Analysis Subcommittee. That reduction could lower PJM's 2027 load forecast, which would affect the grid operator's backstop procurement target. With that reduction, the procurement could be as small as roughly 630 MW, according to the note.

The procurement could also shrink if data center developers enter into bilateral contracts with power suppliers.

Even so, an analysis by Charles River Associates, discussed Monday by the subcommittee, found that PJM could face a shortfall of roughly 11.5 GW by 2030. PJM hired CRA to provide an independent data center demand forecast.

Under the proposal, PJM will close the RBP bid window on March 28, with the final procurement target and supply amounts determined on April 28, the grid operator said Thursday. PJM would post the results on May 10.